The Team on site have made some great progress that we wanted to share with you.
We’ve successfully installed and tested the new east main water valve and its operating equipment. The new drainage valves are also in place, and the existing drainage pipe has been cleaned and checked. Temporary scaffolding has now been removed, and the original floor has been fully reinstated.
The project is now largely complete, with just one final step remaining.
If you have any questions you'd like to ask us, please don’t hesitate to get in touch!