Project Update 14/04/2026
From "Tursdale Sewer Network Improvements"
Go to the project
Hi everyone,
As you maybe aware the team have experienced some delays while work has been re-designed, but are now progressing.
The team have now made the connection into the existing wet well for the new drainage outfall and continuing to excavate for the new drainage lines. In order to maintain progress, the team are managing the groundwater on a daily basis.
The final section of topsoil from the compound towards the Old Mill is being stripped this week under an archaeology watching brief and will be sealed and completed by the end of the day.
We will continue to provide updates as work progresses. Should you have any questions, please comment on this page or contact us at NWL.Customer@esh.uk.com.
Thank you for your time
The Project Team
