Project Update 14/04/2026
From "Fenham Service Reservoir"
Go to the project
Hi everyone,
The Team on site have made some great progress that we wanted to share with you.
We’ve successfully installed and tested the new east main water valve and its operating equipment. The new drainage valves are also in place, and the existing drainage pipe has been cleaned and checked. Temporary scaffolding has now been removed, and the original floor has been fully reinstated.
The project is now largely complete, with just one final step remaining.
If you have any questions you'd like to ask us, please don’t hesitate to get in touch!
Many thanks,
The Project Team
Comments
Commenting is not possible because this project is currently not active.
Total likes: 1, total dislikes: 0
. You can no longer react to ideas in Fenham Service Reservoir. You can no longer react to ideas in Fenham Service Reservoir
Share
Posted by
Current status
Update
