Hi everyone,

Here’s the latest update on our erosion protection work at Craster.

Our team has continued clearing stone and sand from the access road along the foreshore. We’ve also started replacing the damaged steps with a new set of steps.

We’ve carried out some small repairs to the existing concrete structures and completed repairs to sections of the sea wall.

🌱 What’s happening next?

Over the coming days, we plan to:

  • Finish the concrete work for the new steps.
  • Place the remaining protective rock next to the steps.
  • Start landscaping and gardening work to restore the area.
  • Finish clearing the remaining stone from the access road once work around the steps is complete.
  • Start removing temporary fencing, equipment and materials that are no longer needed.

Thank you for your patience while we carry out this work.