Project Update 12 October 2026

From "Low Worsall Water Pumping Station"

Go to the project

Hello everyone

We would like to give you all a little update of what has been happening over the past month on site!

  • Silt removal is progressing well, with work now underway on the fourth and final chamber.
  • The old bar screens have been removed from 2 of the 4 chambers.
  • Surveys have been completed on 2 of the 4 chambers.

If you have any questions, please feel free to drop a comment into the comment box below and a member of the Project Team will respond to you!

Many Thanks

The Project Team