Project Update 12/05/2025
From "Coundon Burn Sewer"
Go to the project
Good Morning, works are progressing well at Coundon Burn.
The team have commenced the installation of the compound and haul road and have completed installation of the compound hoarding and easement fencing.
Archaeologists have excavated and backfilled 11 trial holes along the proposed route of the new drainage run. There were no significant findings during excavations.
A Dutch ford has been installed across the watercourse to enable the team and machinery to access the working area.