A quick update on our works around South Moor as follows:
We would firstly like to thank residents and all road users for their patience and understanding whilst we carried out essential works on Park Road, which required a road closure. The work went well and was completed before expected.
We are currently working along Rydal Avenue upsizing the combined network. A rolling road closure will be in place over the next couple of months, which may require residents to take alternative routes.
Phase 1 is imminently complete on Keswick Road and Windermere Terrace for the new combined Sewer. Phase 2 will follow later in the year.
The surface water installation is due to commence over the next couple of weeks on the grassed area in between Greenlands and Grasmere Terrace.