Project Update 11/11/2025
From "Coundon Burn Sewer"
Go to the project
Hi all,
Please see an update below on the progress of works at Coundon Burn:
The team have completed construction of manhole no.10 and have completed open cut drainage works between the Attenuation Tank and manhole no.10, adjacent to the site entrance.
Three riser chimneys have been installed to the roof of the completed attenuation tank structure.
The team completed construction of the Hydrobrake Flow control manhole to the West of the Attenuation Tank.
Backfilling and compaction of attenuation tank structure continues, with stockpiled selected excavated materials.
Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.
Thanks,