Project Update 11/07/2025
From "Storm Overflows Environmental Improvements"
Go to the project
Hi everyone,
We are currently working on Stanghow Road digging a trench to install a 225mm drain using 2 way traffic lights.
We are also excavating a trench within the Parish council land including the Parking Bays to lay a 450mm drain. Parking bays will have road plates applied after excavation work for access to maintain access to the Village Hall. Residents of Meadowdale Court still have access for parking.
We would like to thank all residents of Stanghow Road and Meadowdale Court for their patience and understanding whilst we complete these works.
Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.