Project Update 11/06/2025 - Stanghow Road, Lingdale

From "Storm Overflows Environmental Improvements"

Go to the project

Good Morning

The team are making good progress around Lingdale.

Auger Bore works are still in progress on high street to Stanghow Road, moving into Meadowdale Court week commencing 16 June 2025. Works will take approximately 4 weeks in this area and will include a parking bay suspension at the Village Hall.

The installation of pipework at the top of Balmoral Road will be complete by Friday 13 June, moving to the final stretch of pipework at the bottom of Balmoral Road.

Pipework installation on Stanghow Road will start week commencing 16th June for approximately 10 weeks using a rolling traffic light system.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.