Project Update 10 August 2026

From "Sedgeletch Environmental Improvements"

Go to the project

🚧 Work Due to Start at Sedgeletch

Following the completion of our preparation work, we are now getting ready to begin the main construction phase of the project.


📅 When will work take place?

Subject to final approvals, construction is expected to begin from 10 August 2026 and continue until summer 2027.

Working alongside our partner Avove, we'll be carrying out improvements that will help ensure our treatment works continues to serve the local community while protecting the environment.


👷 What work will be taking place?

The project includes:

  • Building a new pumping station within Sedgeletch Sewage Treatment Works
  • Installing around 3.7km of new underground pipework
  • Creating a new discharge point at the River Wear for treated water

To complete this work safely and efficiently, temporary construction compounds will be set up at several locations, including:

  • Sedgeletch Sewage Treatment Works
  • Elba Park
  • The Lambton Estate area
  • Near the River Wear outfall location

🚦 How might this affect you?

During the work, you may notice:

  • Increased construction activity in the area
  • Construction vehicles and machinery
  • Some additional noise during working hours

Our normal working hours will be 8:00am to 6:00pm, although these may occasionally vary when needed.

🚗 Traffic management

Temporary traffic management will be required on the A182 as part of the project.

Current plans include:

  • A temporary slip road closure for approximately 7 to 8 weeks
  • A temporary lane closure on the A182 for approximately 5 weeks

These arrangements are subject to final approval and may change as plans are finalised. We'll share further updates before any restrictions are introduced.

🌳 Access and local areas

As work progresses, you may see activity within Elba Park and the surrounding area.

There may also be some temporary changes to access around the Lambton Estate while construction compounds are established. Once this initial work is complete, any impact on access is expected to reduce significantly.

We're also reviewing whether a temporary footpath diversion may be needed near the River Wear. If this becomes necessary, we'll provide further information in advance.


Thank you for your patience

We'll do everything we can to minimise disruption and keep you informed throughout the project.

Thank you for your patience and understanding while we carry out these important improvements to help protect and enhance the local environment.

If you need any additional support during the work, or have any questions, please get in touch with us.


📢 As the project progresses, we'll share regular updates to keep you informed about what's happening and what to expect. To stay up to date, click the blue Follow button.

💬 Your views are important to us.

If you have any questions, feedback, or need additional support, please leave a comment below. A member of our project team will be happy to help

Comments

Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.

Share

Current status

Update