How unpredictable is this weather, hope you are making the most of the sunshine though?
Thought I would just give you an update on the progress we have made here on Ovingham.
Our works over the past month have progressed steadily, with the installation of the primary steel beams which will suspend the new deck for the new screens now completed. This represents a key milestone on the scheme as this has allowed us to commence demobilisation and removal the 500t crane from site and set up ready for the secondary steelwork installation & deck along with the mechanical & electrical install ahead of the new screens being delivered in early 2026.
We once again would like to thank you all for your patience and continued support while the works continue. If you have any questions or issues relating to the project, feel free to get in touch, using the contact details provided.