Project Update 09/06/2025
From "Westerton Reservoir Abandonment & Pumping Station"
Go to the project
Good Morning
The team have been very busy at Westerton and have completed the following works:
- Tapped into the Derwent water main to get the main feed.
- Excavated for the booster station and Flow meter.
- Welding the pipes together ready to install in the field.
- Trial holes have started in the village week commencing 02 June 2025, to locate where we are going to tie into the existing main. Traffic management will be in place for approximately 3 weeks.
Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.
Thanks,
Alice