Project Update 09/02/2026

From "Springwell Enhancements Project"

Go to the project

Hi everyone,

I’m pleased to share this week’s update, outlining what you can expect to see on site over the next week.

North East access – drainage installation is underway, with stone laying to follow.

Kerb installation - scheduled for the end of this week, progressing from the North East access through to the West side.

Southern Access - Remaining drainage works will also be completed by the end of the week, enabling concrete pouring to begin as planned.

We’re still collecting votes on the colour of the North East Access Road, and we’d love to hear from you. Please take a moment to have your say!

 Click here to select your preferred option

Should there be anything you’d like to ask us regarding the project, please feel free to add a comment below and a member of the Team would be happy to help.

Many thanks,

The Project Team