We would like to share an update on the progress of the Northumbria Integrated Drainage Partnership (NIDP).
Over the past year, we alongside our delivery partner, Seymour Civil Engineering have been carrying out detailed investigations of the wastewater network in and around The Leas, Cragside and The Meadows areas. This important work has taken longer than initially anticipated; however, it has enabled us to develop plans that we are confident will deliver a safe and sustainable solution to help reduce flood risk and support the community in the long term.
What will happen
We are now ready to begin work on site within the estate. This will include the installation of new wastewater infrastructure, which will be delivered in three phases to help minimise disruption. Each phase will require a temporary road closure on sections of the carriageway, which will restrict vehicle access on the dates shown below. Pedestrian access will be maintained at all times.
- Phase 1: Works will take place in The Leas cul‑de‑sac from 13 July 2026 to 4 December 2026.
- Phase 2: Works will move onto the main section of The Leas (turning left from the cul‑de‑sac) from 18 October 2026 to 4 December 2026.
- Phase 3: The final phase will progress along The Leas to the right of the cul‑de‑sac from 1 December 2026 to 29 January 2027.
We would like to invite you to attend a customer information event. This will take place at Sedgefield Cricket Club, Station Road, Sedgefield, TS21 2BY, on 11 June 2026 between 16:30 and 18:30.
At the event, we will provide further details about the planned works, including road closures and the installation of the rain gardens. We will also outline what to expect during the programme and be available to answer any questions you may have.
We look forward to meeting you and thank you for your understanding and support as we deliver these important improvements