Project Update 04/11/2025

From "Middlesbrough Gresham Road"

Go to the project

Hi everyone,

We recently wrote to you to provide our information regarding the reinstatement of Gresham Road.

Further discussions with the project team, sub contractors and Middlesbrough Borough Council have taken place which have led to some changes in our resurfacing plan.

The resurfacing works will now take place on 11th – 13th November.

We have been able to reduce the programme from 5 days to 3 days by changing our traffic management to stop and go signs instead of a full road closure.

To ensure we can complete the project safely and efficiently, we will require residents to move their vehicles from the designated area temporarily until the work is completed.

If there are any questions, concerns or assistance required for relocating your vehicle, please speak to a member of the site team on 07866830487.

Or email the team at MMBcustomerserviceteam@mottmac.com

We appreciate the work we do can be disruptive to local communities, so we would like to take this opportunity to say thank you for your patience and cooperation whilst working in your area.

Thank you,

The Project Team