Project Update 04/03/2026

From "Springwell Enhancements Project"

Go to the project

Hi everyone,

Here is this week’s update on the work you may notice around the reservoir site.

South of the Reservoir

  • Backfilling to the southern slope of the reservoir is now complete.
  • Preparations for concrete pours are underway, with work expected to begin next week.
  • SuDS drainage connection works will also begin today.

North of the Reservoir

  • Preparation works will begin this week to ensure the area is ready for surfacing next week.
  • The first phase of surfacing will cover the section up to the hammerhead/turning circle.

Traffic Management & Topsoil Relocation

The team remains on schedule for Monday 9th March, when traffic management will be introduced. Once this is in place, the team will begin preparing the area, with topsoil relocation expected to start later in the week / early the following week.

Full details on the traffic‑light locations and the planned topsoil relocation route are available in last week’s update.

Fence Installation

Fence installation is planned to begin toward the end of this month and continue into April.

We will share further information as we approach the start of this work.

Please add a comment in the box below if you have any questions, and a member of the Project Team will respond accordingly.

Many thanks,

The Project Team

Comments

Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.

Share

Current status

Update