Project Update 01/04/2026
From "Springwell Enhancements Project"
Go to the project
Hi everyone,
Please find below an update outlining the planned on-site activities for the next two weeks, including arrangements as we head into the Easter break.
Due to unforeseen circumstances, fencing works did not begin as scheduled last week. These works will now commence this week, starting on the Eastern side of the reservoir and continuing throughout April.
The traffic management that is currently on Mount Park Road will be moved off the road and won't be in use during the Easter Weekend. This will be temporarily suspended from Thursday 2 April until Tuesday 7 April.
W/C 30 March
- As part of the Site Compound reduction, several cabins will be removed and general tidy‑up works within the compound will continue.
- Footpath construction will take place in select areas around the reservoir to support future maintenance access.
- Topsoil works around the North Access Road will continue, with the aim of completing this by the end of the week.
W/C 6 April
- Compound reduction will continue along with stone will be removed from some areas.
- Fencing installation will progress, moving to the Southern side of the reservoir.
- At the Southern entrance of the reservoir, tarmac will be laid as part of the ongoing road construction.
If you have any questions, please feel free to leave a comment in the box below. A member of the Project Team will be happy to help.
We hope you enjoy the long weekend.
Many thanks,
The Project Team