Killingworth Lake & Grassholm Place - Project Update 30 October 2026

From "Ouseburn Wastewater Improvements"

Go to the project

Hello,

We wanted to keep you informed with an update on the recently completed works at Killingworth Lake, as well as details of upcoming works at Grassholm Place.

Killingworth Lake

Works at Killingworth Lake are now complete.

You may still notice our presence in the area over the coming weeks while we carry out a small number of minor remedial works. We do not anticipate these activities causing any disruption.

We would like to thank the local community for their continued patience and support throughout the project. If you have any questions, please leave a comment below and a member of the project team will be happy to help.

Grassholm Place

Our trusted delivery partner, Esh, will begin work at Grassholm Place from Wednesday 4 November, with works expected to continue for approximately four months.

Our site compound will be located behind Grassholm Place, Falcon Place and Sandpiper Place. A map is included below showing our working area, along with the access routes that construction vehicles will use to enter and leave the site.

To enable safe access to the working area, the existing bollards at the end of Grassholm Place will be temporarily removed and reinstated once works have been completed.

Working hours will be Monday to Friday, 9:00am to 5:00pm. However, residents may notice site staff arriving before 9:00am to prepare for the working day.

We recognise that these works may cause some inconvenience to local residents and would like to reassure you that we will do everything we can to keep disruption to a minimum while the project is underway.

If you have any questions, please leave a comment below and a member of the project team will get back to you.